Pedestrian & Cycle Bridge,
Finzels Reach
Project Images
Project Details

Role: Concept/Senior Architect

RIBA Stages: 0 to 7
Project Value: £3.7m.

Client: Cubex Land Ltd

Funder: Palmer Real Estate.
Piling Contractor: Andrew Scott

Bridge Fabricator: CTS

Cladding Subcontractor: Mouldcam

 

Activities:

 

  • Feasibility and Design Concept;

  • Identification and resolution of harbourmaster and stakeholder interests;

  • Identifying and incorporating national guidance and standards for pedestrian and cycle bridge design;

  • Coordinated bridge fabricator and structural piling information ensuring key design parameters were maintained;

  • Sourced a suitable specialist and commissioned an independent health and safety review of implications to water users (completed by the Cardiff Harbourmaster);

  • Completed all planning application information and commissioned/coordinated supplementary consultant reports;

  • Discussed the bridge cladding requirements with several potential suppliers and obtained quotations;

  • Detailed design coordination;

  • Monitored construction drawings and processes to ensure the consented scheme was delivered.

 

 

 

 

 

Declan O'Donnell